status
status
accepted

Enforce audit self-sufficiency — no upstream host contract

PIEXTENSIO-10 (promotion governance) and PIEXTENSIO-13/15 (host contract and enforce gates) conditioned the allow-only Enforce authority on a formal host contract in upstream @gotgenes/pi-permission-system: acknowledged review writes, capability versioning, pre-link enrollment, and a LocalUserAuthorizer-only human-decision marker. We decided to drop that dependency: every guarantee Enforce needs will be provided by the Judge package itself, and the upstream stays untouched at zero changes.

Why the original design was wrong

Not "too early" — structurally wrong. Every contract item is complexity the upstream maintainer must carry forever, serving a plugin he does not use. His own users gain nothing from it. A PR of that shape sits in the queue forever (observed: upstream has unprocessed PRs already). Designing our audit needs as host obligations is asking someone else to pay for our feature.

The "self-recording is untrustworthy" argument also failed scrutiny under the actual threat model: this Judge runs on the operator's own machine, single-user. The Judge can be buggy but has no motive to deceive. Bugs are covered by in-process self-checks; "independent third-party audit" is an enterprise-multi-tenant requirement we do not have. (The original patches were also lost with ~/Projects/.workspace/ cleanup and were never pushed — the dependency was not just unwanted but gone.)

What self-sufficiency means concretely

  1. Judge-owned audit log, separate file from the permission-system review log (which also solves an operational pain: that log is ~850KB of mixed events). Append + fsync per record; a failed write marks the runtime unhealthy, and the Enforce truth table's telemetry gate refuses authority while unhealthy. This is the self-implemented version of "acknowledged writes".
  2. Human-decision attribution at the consumption side. Real-human decisions are distinguishable by event shape (approved/denied from the dialog vs session_approved/ auto_approved/infrastructure_auto_allowed), verified against live data in the 2026-08-17 TUI cohort (round 5 showed forwarded auto_approved double-writes). The analyzer filters cohort rows on this shape instead of the upstream marking humans.
  3. Denominator redefined as "asks the Judge itself received" (waiting rows in the Judge log), not upstream pre-link enrollment. Self-consistent bookkeeping; the PIEXTENSIO-10 floor math applies to this denominator unchanged.
  4. The truth-table gate hostContractPresent becomes a local self-check gate (audit log healthy). Mechanically identical in effect: today's production state already defers unconditionally.

What is explicitly not weakened

  • The PIEXTENSIO-10 floor (100 qualified rows, zero false allows, per-segment) stands, computed on the self-owned log.
  • Allow-only semantics stand: the Judge never denies; every uncertain case defers to the human dialog.
  • Fail-closed stands: audit unhealthy → defer; malformed evidence → defer; unknown state → defer.

Consequences

  • PIEXTENSIO-15 is cancelled (single-consumer upstream feature = unmaintainable dependency). Its lessons stay here.
  • If the upstream ever ships an equivalent contract on its own initiative, the Judge may adopt it later; nothing in this design blocks that. Revisit trigger: multi-user / multi-tenant deployments where the "buggy-but-honest" threat model no longer holds.